At HYDRAC SA's headquarters in Douala, Citiva Consult led the project management of the completion works of a non-destructive testing training centre and the construction of a personnel certification centre.
Project Overview
At HYDRAC SA's headquarters in Douala, Citiva Consult provided project management (maîtrise d'œuvre) for two linked operations: the completion of a non-destructive testing (NDT) training centre and the construction of a new centre dedicated to the certification of NDT personnel.
This mission followed the design study Citiva Consult had previously carried out for HYDRAC's training centre. Moving from design to construction with the same partner gave the client continuity: the team supervising the works knew the project, its objectives and its technical choices from the inside.
As project manager, Citiva Consult represented the client on site, coordinated the contractors and kept the works aligned with the design, the schedule and the budget.
Project gallery
04 photos



Context And Objectives
Training and certifying NDT technicians requires facilities that meet the expectations of industry and certification bodies. For HYDRAC, the stakes were to:
- Complete the training centre and deliver a new certification centre on its head-office site.
- Ensure the works matched the design and the expected level of quality.
- Keep control of the schedule and the budget while the site remained in operation.
Scope Of Work
- Project management of the training centre completion works.
- Project management of the certification centre construction.
- Representation of the client and coordination of the contractors.
- Site supervision and quality control.
- Schedule follow-up and progress reporting.
- Follow-up of the works up to their acceptance.
Our Approach
Representing the client on site
Project management means acting as the client's technical representative. Our team was the link between HYDRAC and the contractors: answering technical questions, validating proposals and making sure decisions were taken at the right time.
Coordinating the contractors
Building and completing two centres involves several trades working on the same site. We organised the coordination between them so that work sequences fitted together, interfaces were managed and delays caused by one trade did not cascade onto the others.
Controlling quality
Works were checked against the design and the technical specifications. Regular site inspections made it possible to spot non-conformities early and have them corrected before they were covered up by subsequent works.
Keeping schedule and budget under control
Progress was monitored against the schedule, and the client was kept informed through regular reporting. Any change to the scope was assessed for its impact on cost and timing before being approved.
Working on an operating site
The works took place on HYDRAC's head-office site. Site organisation therefore had to take into account the client's ongoing activities, with attention paid to access, safety and the limitation of nuisances.
Results
- A completed NDT training centre and a new personnel certification centre for HYDRAC SA.
- Works supervised and checked against the design and specifications.
- A client kept informed and in control throughout the project.
This mission shows the full range of Citiva Consult's support: from the first design study to the supervision of works on site.